Supercomputers Rock!

Proposed Campuses·Pennsylvania·updated September 9, 2026

Aligned Project Phoenix

Shippingport Borough · South Side Area SD · Beaver County·Aligned Data Centers, on the former Bruce Mansfield coal plant

Size
Up to 3.6 GW of on-site generation next to three data halls
Taxable real estate (our method)
$36 billion
Estimated annual tax
+$1.39 billion a year
City, school, and county combined, at today’s millage, if the campus is assessed at our $10 million/MW method.
Current assessed tax base, the base after this campus is added, and estimated annual tax at today’s millage
LocaleTax base todayTax base if it is builtEst. annual tax
Shippingport Borough$190 million$36.2 billion190× today’s assessed value+$91 million
South Side Area School District$851 million$36.9 billion43× today’s assessed value+$362 million
Beaver County$15.6 billion$51.6 billion3.3× today’s assessed value+$936 million

Three two-story halls totaling about 2 million square feet on the old Bruce Mansfield site in Shippingport, plus a 70-acre gas-generation pad. Shippingport council granted zoning modifications in 2026. The 3.6 GW figure is Frontier’s planned generation at the industrial park — the same caveat as Homer City: generation is not a signed IT lease.

Local coverage has put the campus in the $10 billion neighborhood. Aligned closed a $223 million land purchase in 2026.

Shippingport’s assessed tax base is $190 million; South Side Area is $851 million. Even a slice of taxable halls would dominate both. Beaver County is large ($15.6 billion) and millage is high (26 mills).

PA Legislators

Loading district information...

Open on the map