- Size
- 350 MW contracted, with a 1 GW Pennsylvania pipeline
- Taxable real estate (our method)
- $3.5 billion
- Estimated annual tax
- +$336 million a year
- City, school, and county combined, at today’s millage, if the campus is assessed at our $10 million/MW method.
| Locale | Tax base today | Tax base if it is built | Est. annual tax |
|---|---|---|---|
| Nesquehoning Borough | $63 million | $3.56 billion57× today’s assessed value | +$73 million |
| Panther Valley School District | $140 million | $3.64 billion26× today’s assessed value | +$202 million |
| Carbon County | $1.76 billion | $5.26 billion3.0× today’s assessed value | +$61 million |
Former waste-coal plant in Nesquehoning. Bitfarms’ August 5, 2025 release named T5 as partner to advance an HPC/AI campus and pointed to a 1 GW pipeline in Pennsylvania. Bitfarms’ CEO later told Data Center Dynamics the site has a firm contract for 350 MW by 2028, with room toward 500 MW or more.
We size the assessed-value sketch on the 350 MW that is actually contracted, not the 1 GW aspiration. That is still $3.5 billion of taxable buildings against a $63 million borough and a $140 million school district.
PA Legislators